Active works are being carried out on several sections of the H-03 Zhytomyr-Chernivtsi highway.
Bridge over the river Buzhok:
- Construction was completed and traffic was resumed on the left driveway
- Dismantled the old bridge, arranged brown piles, cabinet walls and concreting of supporting parts
- We are preparing for the installation of girder beams.
KM 163-166:
- Finished the installation of the upper layer of the coating ShchMA 20 on the right aisle
- The device of strengthening of slopes of an embankment is carried out
- Arrangement of side stones and formation of roadsides is carried out
- In the near future we will finish the installation of the upper layer on the left driveway, lighting and arrangement of the road will be installed.
KM 167-170:
- The bridge over the Gulyanka River was repaired
- Finished the installation of the upper layer of the coating ShchMA 20 on the left aisle
- We finish the device of the top layer on the right passage
- Works on installation of external lighting, spillways and roadsides are being carried out.