Works on the highway H-03 Zhytomyr – Chernivtsi

Active works are being carried out on several sections of the H-03 Zhytomyr-Chernivtsi highway.

Bridge over the river Buzhok:

  1. Construction was completed and traffic was resumed on the left driveway
  2. Dismantled the old bridge, arranged brown piles, cabinet walls and concreting of supporting parts
  3. We are preparing for the installation of girder beams.

 

KM 163-166:

  1. Finished the installation of the upper layer of the coating ShchMA 20 on the right aisle
  2. The device of strengthening of slopes of an embankment is carried out
  3. Arrangement of side stones and formation of roadsides is carried out
  4. In the near future we will finish the installation of the upper layer on the left driveway, lighting and arrangement of the road will be installed.

 

KM 167-170:

  1. The bridge over the Gulyanka River was repaired
  2. Finished the installation of the upper layer of the coating ShchMA 20 on the left aisle
  3. We finish the device of the top layer on the right passage
  4. Works on installation of external lighting, spillways and roadsides are being carried out.

11.11.2021