We continue to carry out fundamental works on the H-03 highway on the section Khmelnytskyi – Starokostiantyniv

  • The old Soviet-era pipe was dismantled
  • A new corrugated metal culvert MultiPlate has been installed
  • The pipe was wound with two layers of geotextile and a layer of compacted loam around the pipe
  • The culvert was backfilled
  • Arranged waterproof layer over the MGC of the geomembrane
  • The two-layer protection of a geomembrane from geotextile (500 g / m²) is arranged
  • Currently, we continue to compact the loam with rammers and soil rollers.